Construction Package 12
Package No : CP-12
Name of EPC Contractors : M/s. Dilip Buildcon Ltd.
Length in Km: 45.645
LOA Issued date : 30.08.2018
Chainage details : Package 12, from Km. 532.094 To Km. 577.739 in section – Village Pathare Kh. to Village Sonari in District Nashik
Name of Authority Engineers Consultant : M/s. S.A. Infrastructure Consultants Pvt. Ltd.
LOA Issued date : 20.11.2018
Description
Scope
WIP
Completed
Major Structures
Major Bridges
07
07
–
Minor Structures
Minor Bridges
18
09
09
VUP
29
–
29
LVUP
23
–
23
CUP and PUP
11
–
10
Box Culverts
30
01
29
Other Structures
Interchanges
01
01
–
Total Structure
119
18
101
Activities
Scope
WIP
Completed
Balance
Clearing & Grubbing (C&G)
43.5
0.0
43.5
0.0
Embankment / Sub Grade Top (Emm-SG)
43.5
12.9
29.4
3.0
Granular Sub-Base (GSB)
43.5
3.0
24.3
16.2
Dry Lean Concrete (DLC)
43.5
3.0
19.7
20.8
Pavement Quality Concrete (PQC)
43.5
1.7
18.0
23.8