Construction Package 13
Package No : CP-13
Name of EPC Contractors : M/s. BSCPL GVPR JV
Length in Km: 45.640
LOA Issued date : 29.09.2018
Chainage details : Package 13, from KM. 577.739 TO KM. 623.379 (Section – Village Sonari to Village Taranganpada) in District Nashik
Name of Authority Engineers Consultant : M/s. S.A. Infrastructure Consultants Pvt. Ltd
LOA Issued date : 20.11.2018
Description
Scope
WIP
Completed
Major Structures
Flyover/Viaduct
03
03
–
Major Bridges
01
01
–
Minor Structures
Minor Bridges
14
06
03
VOP
14
04
–
VUP
13
02
09
LVUP
20
02
16
CUP and PUP
07
–
07
Box Culverts
54
07
31
Other Structures
Interchanges
01
01
–
Total Structure
127
26
66
Activities
Scope
WIP
Completed
Balance
Clearing & Grubbing (C&G)
42.5
39.6
1.2
1.7
Embankment / Sub Grade Top (Emm-SG)
42.5
18.0
5.5
19.0
Granular Sub-Base (GSB)
42.5
13.8
0.4
28.3
Dry Lean Concrete (DLC)
42.5
9.8
0.0
32.7
Pavement Quality Concrete (PQC)
42.5
0.0
0.0
42.5