Construction Package 2
Package No : CP-2
Name of EPC Contractors : M/s. Afcon Infrastructure Ltd.
Length in Km: 58.413
LOA Issued date : 30.08.2018
Chainage details : Package 2, from Km. 31.000 to Km. 89.413 (Section â Village Khadki Amgaon to Village Pimpalgaon) in District Wardha
Name of Authority Engineers Consultant :M/s. Consulting Engineers Group Ltd. in association with SKES
LOA Issued date : 17.10.2018
Description
Scope
WIP
Completed
Major Structures
Flyover/Viaduct
08
04
03
Major Bridges
03
01
02
ROB
02
02
–
Minor Structures
Minor Bridges
17
01
16
VOP
2
–
–
VUP
19
–
19
CUP & PUP
12
–
12
Canal Bridge
07
–
07
Box Culverts
81
02
77
Other Structures
Interchanges
02
02
–
Interchanges
–
–
–
Total
153
12
136
Activities
Scope
WIP
Completed
Balance
Clearing & Grubbing (C&G)
55.8
0.0
55.8
0.0
Embankment / Sub Grade Top (Emm-SG)
55.8
10.1
45.7
0.0
Granular Sub-Base (GSB)
55.8
42.7
0.9
12.2
Dry Lean Concrete (DLC)
55.8
0.0
37.1
18.7
Pavement Quality Concrete (PQC)
55.8
0.0
23.7
32.1