Construction Package 6
Package No : CP-6
Name of EPC Contractors : M/s. APCO Infratech Pvt. Ltd.
Length in Km: 36.100
LOA Issued date : 30.08.2018
Chainage details : Package 6, From Km. 259.900 to Km. 296.000 (Section – Village Belgaon to Village Parda) in District Buldhana
Name of Authority Engineers Consultant : M/s. Arvee Associates Architects Engineers & Consultants Pvt. Ltd. In Association with Technovision Consultants
LOA Issued date : 17.10.2018
Description
Scope
WIP
Completed
Major Structures
Major Bridges
01
01
–
Minor Structures
Minor Bridges
14
04
10
VOP
04
04
–
VUP
07
–
07
LVUP
02
–
02
CUP and PUP
22
–
22
POP
02
02
–
Box Culverts
20
–
20
Other Structures
Interchanges
01
01
–
Total Structure
73
12
61
Activities
Scope
WIP
Completed
Balance
Clearing & Grubbing (C&G)
36.1
0.0
36.1
0.0
Embankment / Sub Grade Top (Emm-SG)
35.0
2.3
31.3
1.5
Granular Sub-Base (GSB)
35.0
1.2
27.4
6.4
Dry Lean Concrete (DLC)
35.0
0.6
27.0
7.5
Pavement Quality Concrete (PQC)
35.0
0.3
23.4
11.3