Construction Package 9
Package No : CP-9
Name of EPC Contractors : M/s. Megha Engineering & Infrastructure Ltd
Length in Km: 54.400
LOA Issued date : 30.08.2018
Chainage details : Package 9, from Km. 390.445 to Km. 444.485 (Section – Village Bendewadi to Village Fatiwabad) in District Aurangabad
Name of Authority Engineers Consultant : M/s. Yooshin Engineering Corporation in J/V with Multimedia Consultants Pvt. Ltd. and in Association with JS Environics Consultants Pvt. Ltd.
LOA Issued date : 06.11.2018
Description
Scope
WIP
Completed
Major Structures
Flyover/Viaduct
3
03
–
Major Bridges
01
01
–
Minor Structures
Minor Bridges
40
12
18
VOP
01
–
–
VUP
17
07
10
LVUP
06
01
05
CUP and PUP
17
01
15
Box Culvert
72
06
58
Other Structures
Innterchange
01
01
–
Tunnel
01
01
–
Total Structure
159
33
106
Activities
Scope
WIP
Completed
Balance
Clearing & Grubbing (C&G)
54.0
0.0
31.0
0.4
Embankment / Sub Grade Top (Emm-SG)
52.4
3.4
42.8
6.3
Granular Sub-Base (GSB)
52.4
8.2
34.6
9.7
Dry Lean Concrete (DLC)
52.4
6.6
28.0
17.8
Pavement Quality Concrete (PQC)
52.4
8.8
18.6
25.0