6 lane Road

Overall Construction Update

Overall Project Status- Road Works

Overall Project Status- Road Works :

*Status as on 31st May, 2021

Activity Description

Scope

Completed

WIP

Balance

% Completed

% WIP

% Balance

C&G

660.7

625.2

21.5

14.0

98.41%%

1.30%

2.12%

100.00%

EMB/SG

647.5

452.7

98.9

95.8

79.17%

12.89%

14.80%

100.00%

GSB

657.8

405.4

21.6

230.7

72.99%

2.72%

35.80%

100.00%

DLC

659.1

363.4

13.7

282.0

69.18%

0.61%

42.79%

100.00%

PQC

659.1

281.4

14.4

363.3

60.77%

1.62%

55.11%

100.00%

Overall Project Status- Structures

Overall Overall Project Status- Structures :

*Status as on 31st May, 2021

Description

Scope

WIP

Completed

% Completed

%WIP

Major Structures

Flyover/Viaduct

65

47

14

14%

77%

Major Bridges

32

17

12

6%

81%

ROB

8

5

2

0%

75%

Minor Structures

Minor Bridges

274

57

188

47%

44%

VOP

65

18

2

2%

26%

VUP

189

25

152

69%

20%

LVUP

110

10

94

79%

15%

CUP and PUP

209

10

198

89%

8%

WOP

3

0%

0%

WUP

3

3

0%

100%

POP

19

4

2

11%

21%

Canal Bridge

20

2

18

65%

9%

Box Culverts

672

29

611

85%

9%

Other Structures

Interchanges

24

20

0%

75%

Tunnel

6

6

0%

100%

Total Structure

1,699

345

1,180

66%

23%

Manpower

Workforce Status :

Sr. No

Construction Package

Skilled

Technical

Unskilled

Total

1

CP 01

1746

616

225

2587

2

CP 02

1630

1917

183

3730

3

CP 03

1845

129

344

3905

4

CP 04

1146

200

310

1656

5

CP 05

1055

550

149

1754

6

CP 06

961

564

74

1599

7

CP 07

1371

111

400

1882

8

CP 08

921

192

83

1196

9

CP 09

1316

300

153

1769

10

CP 10

1205

818

275

2298

11

CP 11

590

455

84

1129

12

CP 12

43

84

40

167

13

CP 13

1284

956

146

2386

14

CP 14

637

333

117

1087

15

CP 15

752

446

98

1296

16

CP 16

1124

1102

110

2336

Total Structure

17626

10360

2791

30777

Key Highlights

  1. 30,000+ workers Technical, Skilled and Unskilled working along the entire Length of Project.
  2. A team of 500+ members monitoring the work as Authority’s Engineer.
  3. 2700+ Engineers working in 16 packages.

MSRDC Staff

  1. Chief Engineer – 02
  2. Superintending Engineer – 06
  3. Executive Engineer -12
  4. Deputy Engineer – 23

Total MSRDC Staff = 63

Machinery

Machinery Status :

Sr. No

Construction Package

Tipper

Excavators

Dozers /loaders

Graders

Rollers / Compactor

Pavers

Transit Mixer

Total

1

CP 01

134

28

8

8

21

3

27

229

2

CP 02

403

100

19

19

28

3

39

611

3

CP 03

271

91

13

48

50

10

40

523

4

CP 04

265

57

12

31

47

5

46

463

5

CP 05

283

71

18

19

29

2

19

441

6

CP 06

139

36

5

10

16

3

17

226

7

CP 07

215

92

12

21

22

3

28

393

8

CP 08

85

21

6

8

15

3

21

159

9

CP 09

285

91

15

22

29

3

30

475

10

CP 10

263

74

3

30

38

7

32

447

11

CP 11

55

9

4

6

5

2

10

91

12

CP 12

143

21

12

11

22

3

10

222

13

CP 13

1284

1284

1284

1284

1284

956

146

2386

14

CP 14

96

32

4

1

4

0

25

162

15

CP 15

88

54

7

3

4

27

183

16

CP 16

113

46

8

6

12

0

30

215

Total Structure

3089

899

164

263

391

52

424

5282

  • 6000+ Major Equipment’s like Excavators, Dozers, Graders, Pavers , Cranes etc. working dayand night on site.
  • Lot of specialized equipment’s been procured by agencies considering the quantum of work :
  • Slipform PQC Paver 16 m wide is used for laying PQC. One of the most advanced machine available.

    Mobile Crusher plants are procured by the EPC contractor to convert all the possible Excavated material as per the Engineering Requirement

    Heavy Earth Moving Equipment’s are used considering huge Quantities of Cutting and Filling all along the 700 km Length. Equipment’s like the Liebherr Earthmover with Bucket capacity of 4.5 Cum are used in numbers.

    Tunnel Works

    Tunnel Works :
  • Twin Tube Tunnel at 6 Location ( 2 more Locations Proposed )
  • With total tunnelling length more than 21 km
  • Longest Tunnel of Length 7.780 Km near Igatpuri.
  • Typical Specification of Tunnel:

  • Twin Tube Tunnels
  • Width of Tunnel 17.6 m
  • Clear Height of 5.5 m
  • Sr. No

    Tunnel

    LHS

    RHS

    Total Tunnel Length

    1

    CP 09-Tunnel 1

    260m

    260m

    520m

    2

    CP 14-Tunnel 1

    7780m

    7740m

    15520m

    3

    CP 15-Tunnel 1

    267m

    267m

    566m

    4

    CP 15-Tunnel 2

    925m

    1010m

    1935m

    5

    CP 16-Tunnel 1

    928m

    928m

    1856m

    6

    CP 16-Tunnel 2

    463m

    463m

    926m

    Total Tunnel Length

    21323m