Overall Construction Update
Overall Project Status- Road Works
Overall Project Status- Road Works :
*Status as on 31st May, 2021
Activity Description
Scope
Completed
WIP
Balance
% Completed
% WIP
% Balance
C&G
660.7
625.2
21.5
14.0
98.41%%
1.30%
2.12%
100.00%
EMB/SG
647.5
452.7
98.9
95.8
79.17%
12.89%
14.80%
100.00%
GSB
657.8
405.4
21.6
230.7
72.99%
2.72%
35.80%
100.00%
DLC
659.1
363.4
13.7
282.0
69.18%
0.61%
42.79%
100.00%
PQC
659.1
281.4
14.4
363.3
60.77%
1.62%
55.11%
100.00%
Overall Project Status- Structures
Overall Overall Project Status- Structures :
*Status as on 31st May, 2021
Description
Scope
WIP
Completed
% Completed
%WIP
Major Structures
Flyover/Viaduct
65
47
14
14%
77%
Major Bridges
32
17
12
6%
81%
ROB
8
5
2
0%
75%
Minor Structures
Minor Bridges
274
57
188
47%
44%
VOP
65
18
2
2%
26%
VUP
189
25
152
69%
20%
LVUP
110
10
94
79%
15%
CUP and PUP
209
10
198
89%
8%
WOP
3
–
–
0%
0%
WUP
3
3
–
0%
100%
POP
19
4
2
11%
21%
Canal Bridge
20
2
18
65%
9%
Box Culverts
672
29
611
85%
9%
Other Structures
Interchanges
24
20
–
0%
75%
Tunnel
6
6
–
0%
100%
Total Structure
1,699
345
1,180
66%
23%
Manpower
Workforce Status :
Sr. No
Construction Package
Skilled
Technical
Unskilled
Total
1
CP 01
1746
616
225
2587
2
CP 02
1630
1917
183
3730
3
CP 03
1845
129
344
3905
4
CP 04
1146
200
310
1656
5
CP 05
1055
550
149
1754
6
CP 06
961
564
74
1599
7
CP 07
1371
111
400
1882
8
CP 08
921
192
83
1196
9
CP 09
1316
300
153
1769
10
CP 10
1205
818
275
2298
11
CP 11
590
455
84
1129
12
CP 12
43
84
40
167
13
CP 13
1284
956
146
2386
14
CP 14
637
333
117
1087
15
CP 15
752
446
98
1296
16
CP 16
1124
1102
110
2336
Total Structure
17626
10360
2791
30777
Key Highlights
- 30,000+ workers Technical, Skilled and Unskilled working along the entire Length of Project.
- A team of 500+ members monitoring the work as Authorityâs Engineer.
- 2700+ Engineers working in 16 packages.
MSRDC Staff
- Chief Engineer – 02
- Superintending Engineer – 06
- Executive Engineer -12
- Deputy Engineer â 23
Total MSRDC Staff = 63
Machinery
Machinery Status :
Sr. No
Construction Package
Tipper
Excavators
Dozers /loaders
Graders
Rollers / Compactor
Pavers
Transit Mixer
Total
1
CP 01
134
28
8
8
21
3
27
229
2
CP 02
403
100
19
19
28
3
39
611
3
CP 03
271
91
13
48
50
10
40
523
4
CP 04
265
57
12
31
47
5
46
463
5
CP 05
283
71
18
19
29
2
19
441
6
CP 06
139
36
5
10
16
3
17
226
7
CP 07
215
92
12
21
22
3
28
393
8
CP 08
85
21
6
8
15
3
21
159
9
CP 09
285
91
15
22
29
3
30
475
10
CP 10
263
74
3
30
38
7
32
447
11
CP 11
55
9
4
6
5
2
10
91
12
CP 12
143
21
12
11
22
3
10
222
13
CP 13
1284
1284
1284
1284
1284
956
146
2386
14
CP 14
96
32
4
1
4
0
25
162
15
CP 15
88
54
7
3
4
–
27
183
16
CP 16
113
46
8
6
12
0
30
215
Total Structure
3089
899
164
263
391
52
424
5282
Slipform PQC Paver 16 m wide is used for laying PQC. One of the most advanced machine available.
Mobile Crusher plants are procured by the EPC contractor to convert all the possible Excavated material as per the Engineering Requirement
Heavy Earth Moving Equipmentâs are used considering huge Quantities of Cutting and Filling all along the 700 km Length. Equipmentâs like the Liebherr Earthmover with Bucket capacity of 4.5 Cum are used in numbers.
Tunnel Works
Tunnel Works :
Typical Specification of Tunnel:
Sr. No
Tunnel
LHS
RHS
Total Tunnel Length
1
CP 09-Tunnel 1
260m
260m
520m
2
CP 14-Tunnel 1
7780m
7740m
15520m
3
CP 15-Tunnel 1
267m
267m
566m
4
CP 15-Tunnel 2
925m
1010m
1935m
5
CP 16-Tunnel 1
928m
928m
1856m
6
CP 16-Tunnel 2
463m
463m
926m
Total Tunnel Length
21323m