Project Process
Progress of the project:
In the meeting of the Infrastructure subcommittee held on 30.11.2015, the following decisions were taken regarding the construction of the Nagpur-Mumbai Expressway (Samruddhi Highway).
-
Appointment of MSRDC as Implementing agency for the samruddhi project.
-
Adoption of Greenfield Alignment for the project.Introduction of Land Pooling Scheme for the project.
With a view to facilitate surface traffic between Nagpur and Mumbai highways, Hon. Chief Minister announced in the Assembly on 31.07.2015, to build Nagpur-Mumbai Expressway (Samruddhi Highway).
Government Approvals:
Government Approvals:
In the meeting of the Infrastructure subcommittee held on 30.11.2015, the following decisions were taken regarding the construction of the Nagpur-Mumbai Expressway (Samruddhi Highway).
-
Appointment of MSRDC as Implementing agency for the samruddhi project.
-
Adoption of Greenfield Alignment for the project.Introduction of Land Pooling Scheme for the project.
Appointments/ Growth Path:
Highlights of the project
Highlights of the project:
*Status as on 31st May, 2021
Sr. No
Particulars
Values
1
Total length
701 Km
2
Width of the road (ROW)
120 Meters (90Meter for Mountainous roads)
3
No. of Lanes
3+3 lanes (3.00 m wide paved shoulder on both sides and 2.00 m wide clay shoulder)
4
Proposed Vehicle Speed
150 km/ hr (120km/hr for mountainous region)
5
Proposed Interchanges
24
6
No. of newtowns to be developed along the corridor
19
7
No. of Major bridge (over 30 m in length)
32
8
No. of Minor Bridge/ Canal Bridge (less than 30 m in length)
274
Current Position of the project:
Current Position of the project:
- At present 8311.15 hectare land (ROW) required for the project has been acquired and Rs. 5875.93 crore has been paid.
- All 5 DPR packages of the project have received environmental clearance.
- A total of 5 DPR packages of the project have been approved by the Forest Department.
- DPR Package 2 and 5 have received approval from Wildlife Conservation Department
- All the bidders of the project for Package1 to 16, LOA and work starting date have been given. At present, all the work in these packages are in progress.
- Government of Maharashtraâs Revenue and Forest Department published a Gazette notification on 14th November 2018, notifying Nagpur-Mumbai Super Communication Expressway as an important project.
- Exemption has been given for the imposition of leviable ownership on the extraction of secondary minerals required for the project.
- Construction Package 1 to 13 is scheduled to be completed in 30 months and Construction Package 14 to 16 is scheduled to be completed in 36 months. Accordingly, it is planned to complete the entire work of the project by September 2022.
- This highway has been renamed as “Hindu Hrudaysamarat Balasaheb Thackeray Maharashtra Samruddhi Highway” by the government on December 22, 2019.
Progress of the project:
Progress of the project:
*Status as on 31st May, 2021
Sr. No
Description of works
Progress
1
Land acquired through Land Acquisition (%)
90.64 % Km
2
Soil filling / bottom layer work (%)
57.82 %
3
G.S.B (%)
72.99 %
4
D.L.C (%)
69.18 %
5
P.Q.C (%)
60.77 %
-
Out of total 1699 structures, construction of 1286 structures has been completed and construction of 253 structures is in progress.
Still Have a Question?
Maharashtra State Road Development Corporation Ltd
Registered Office Address:
Nepean Sea Road, Priyadarshini Park, Mumbai 400036, Maharashtra,India.
Corporate Office Address :
MSRDC office Premises, K. C. Marg, Near Lilavati Hospital, Bandra (W), Mumbai-400050, India.
IMPORTANT LINKS
ABOUT
Hindu Hrudaysamrat Balasaheb Thackeray Maharashtra Samruddhi Mahamarg aims at providing an impetus to the overall development of rural areas by attracting domestic and foreign investment.
- 1800 233 2233
- 8181818155
- +91- 22 26417893
- info@msdrc.org
MAP