Project Statistics

Key Statistics

Length of Hindu Hruday Samrat Balasaheb Thackeray Maharashtra Samruddhi Mahamarg 701 km
Hindu Hruday Samrat Balasaheb Thackeray Maharashtra Samruddhi Mahamarg route Nagpur to Mumbai
Number of districts the mahamarg passes through 10
Number of talukas connected 26
Number of villages connected by the expressway 392
Number of proposed Krushi Samruddhi Nagar 19
Land required for the project (Expressway + Krushi Samruddhi Nagar) 24,255 acres (9,900 Ha) approximately
Total Project Cost Rs. 55,000 crores approximately
Proposed Project Completion date 2022

Land Requirement


Acres Hectares
For the Krushi Samruddhi Nagar 24,500 10,000
For the Expressway 24,255 9,900
Amenities and facilities along the mahamarg 355 145
Total land requirement 49,110 20,045

Distance of the District HQ Towns From the Expressway

Wardha
0 km
Jalna

0 km
Aurangabad
0 km
Nashik
0 km
Palghar
0 km
Thane
0 km
Washim
22 km
Amravati
26 km
Yavatmal
42 km
Akola
47 km
Hingoli
70 km
Buldhana
75 km
Ahmednagar
87 km
Parbhani
102 km
Chandrapur
125 km
Beed
130 km
Dhule
160 km
Nanded
190 km
Jalgaon
190 km